Update Notice – Summer Construction Works Eyke Parish

To All Eyke Parishioners:

The council have previously sought to provide advance information to all residents about works on the Village Hall 19th July – 1st September, utilisation of the school entrance and playground to access the rear of the village hall and closure of the parish car park 1st August – 1st September for redevelopment by Denbury Developments.

I now need to also make everyone aware of the installation of temporary two-way traffic lights on The Street, Eyke (A1152) in advance of the full road closure required to install the final sewer connection for the new housing development. (Incidentally this will also lead to an improved facility for all exiting users in the village).

Suffolk County Council (Network Assurance) are making the arrangements for the diversionary route; they have asked that we make you aware of the restrictions to this route as early as possible.

Please see details below:

    • Permit reference:LY106SWL00500
    • Name of organisation undertaking the works: Ashwell Construction and Redivac.
    • Principle contractor: Denbury Homes
    • Duration of works:28.07.2025-10.08.2025 for works with lane closure under two-way traffic lights and further Road Closures from 11.08.2025-16.08.2025.

The council and developers are doing all they can to minimise inconvenience and disruption during this period which is intended to utilise the school holiday period to maximum effect and avoid congestion locally 28.07.2025 – 17.08.2025 through to 1.9.2025

These works will be undertaken simultaneously and collaboratively with OpenReach, Anglian Water, and TriConnex in order to minimise the amount of disruption to the residents of Eyke and the surrounding areas.

So, this 6 – week period will be very busy for us all and there will be traffic delays and some disruption locally, especially around the village centre and Church Lane. Please bear with us as the benefit to village facilities going forward will be considerable once we get through this very disruptive period by our normal rural standards.

Please consult the Parish Council Website www.eyke-pc.gov.uk  and the Eyke Parish Council facebook page for further updates. If you do not yet get the parish councils email updates please sign up to the email system via the website as we plan to use it extensively to disseminate further information as it becomes available.

 

Lee M Weavers

Clerk

11.7.2025

Areas Impacted:

  1. Two-way traffic lights on The Street, Eyke 28/07/2025-10.08.2025

2.Road Closure 11.08.2025-16.08.2025